Starting up and testing your SLC 500 control system is a critical step in ensuring the reliability and safety of your automation processes. This guide will walk you through the essential procedures for performing a thorough system startup and initial testing, from inspecting your installation to conducting a dry run. Follow these steps to ensure your system operates smoothly and effectively.
1. Inspect Your Installation
Before you begin the startup process, it's important to inspect your installation to ensure everything is set up correctly. Check all connections, wiring, and components for any signs of damage or incorrect installation. Ensure that all modules are securely mounted in their correct slots and that all power supplies are properly connected.
2. Disconnect Motion-Causing Devices
For safety reasons, ensure that all devices that could cause motion are disconnected. This includes motors, actuators, and other moving parts. Disconnecting these devices prevents accidental movements during the testing phase, which could pose a safety risk to personnel and equipment.
3. Initialize and Test Your Processor
Once you have verified the physical installation, you can initialize and test your processor. Follow these steps:
- Turn on the programming device and configure the controller.
- Name the program, which will become the processor name when downloaded.
- Program a sample test rung that does not affect machine operation.
- Save the program and controller configuration.
- Transfer the controller configuration and sample test program to the processor. The CPU FAULT status indicator should clear once the new program is transferred.
- Enter the Run mode. The processor RUN status indicator should turn on, indicating that the controller is in the Run mode with no CPU faults.
- Monitor and exercise the simple test rung to verify basic processor functions.
If any CPU faults or errors occur, refer to the troubleshooting chapter for recommended actions. For more detailed instructions, consult your programming software and hand-held terminal user manuals .
4. Test Your Inputs
After successfully initializing the processor, it's time to test your inputs. Follow these steps:
- Put the controller into the Continuous Scan Test mode, allowing the processor to scan the I/O and program without turning on any physical outputs.
- Monitor the data in data File 1, the input data file. All configured inputs should be displayed.
- Ensure that the first input slot is shown on the monitor.
- Select the first input device connected to the first input terminal on the input module in the I/O chassis.
- Manually close and open the addressed input device and observe the associated bit status using the programming device monitor function. Also, observe the input status indicator.
If the associated bit status and input status indicator match the input device status, repeat the process for all input devices in the SLC 500 chassis. If there is a mismatch, follow the recommended troubleshooting steps provided in the manual .
5. Test Your Outputs
Now, it's time to test your outputs. Follow these steps:
- Create an output test rung for each configured output module, moving a word of data from the bit file to the output file.
- Save the output test program and current controller configuration.
- Transfer the output test program to the processor and put the controller in the Run mode.
- Monitor the data in data file B3 on the programming device display.
- Enter B3:XX at the address prompt to select the output to be tested, and enter 1 at the data prompt for the address that corresponds to the bit in the output word.
- Observe the output status indicator and the output device. The output status indicator should turn on, and the output device should be energized (unless disconnected to prevent machine motion).
- Reset the data value back to zero, and both the output status indicator and output device should de-energize.
Repeat the process for each output. If the status indicators and output device states do not correspond to the data settings, follow the recommended steps in the Output Troubleshooting Steps section .
6. Enter and Test Your Program
After testing inputs and outputs, enter your program and perform a thorough test. This step ensures that all control logic is functioning correctly and that there are no programming errors. Document any issues and resolve them as necessary.
7. Observe Control Motion
Once the program is entered and tested, observe the control motion to ensure that all actuators, motors, and other moving parts are operating as expected. This step helps identify any potential issues with the control logic or physical setup.
8. Conduct a Dry Run
Finally, conduct a dry run of the entire control system. This involves running the system without any load or physical interaction to verify that all components are working together harmoniously. Monitor the system closely for any abnormalities or errors and make adjustments as necessary.
By following these steps, you can ensure a smooth and successful startup and testing process for your SLC 500 control system. Proper initial testing helps prevent issues down the line and ensures that your automation processes run efficiently and safely.